Home › Flanders: De Lijn goes electric

Flanders: De Lijn goes electric

Where De Lijn and its private operators stand with electric buses in October 2026: the numbers, the 2035 rule, the EUR 400 million turbo, the fleet by maker, the framework contracts, the depots, the charger suppliers, the subsidies, the builders left and the risks. Every figure with a dated source.

Flanders has about 3,800 buses in De Lijn service. The 1,000th electric one entered service on 15 April 2026, and by law every bus must be zero-emission before 2035. Roughly 700 of those 1,000 e-buses belong to the 79 private operators who drive under contract for De Lijn; De Lijn itself had almost 300 and about 800 more on order. In 2025 De Lijn ordered 652 e-buses in one year with a one-off EUR 400 million from the Flemish Government, mostly from BYD, Iveco Bus, VDL and Daimler Buses. The buses are coming faster than the depots: 12 of De Lijn’s ~50 depots had chargers at the end of 2025, permits are contested, and late deliveries cost De Lijn low-emission-zone fines in Ghent. This page sets out what is published, with the date and the source beside every number, for an operator, a municipality or a maker’s European importer who needs the facts rather than the mood.

Headline numbers, October 2026

WhatFigureSource
Buses in De Lijn service, all operators~3,800VRT NWS, 15 Apr 2026
De Lijn’s own fleet2,250 buses and 400 trams (De Lijn’s own boilerplate); 2,149 vehicles counted on 14 Nov 2025De Lijn, 15 Apr 2026; Flemish Parliament, 2 Dec 2025
Private operators’ fleet1,608 buses (Nov 2025); 79 companiesFlemish Parliament, 2 Dec 2025; newmobility.news, 1 Jul 2025
Electric buses in service, all operators1,000th on 15 Apr 2026: “over 700” at the private operators, so about 300 at De Lijn itself (the remainder; De Lijn gives no separate figure)De Lijn, 15 Apr 2026
De Lijn’s own electric buses, last exact count179 of 2,149 vehicles on 14 Nov 2025; 457 e-buses on order that dayFlemish Parliament, 2 Dec 2025
Private operators’ electric share16 % (Jan 2025) → 36 %, 588 of 1,608 buses (1 Jul 2025) → 45 % (Apr 2026)Flemish Parliament, 2 Dec 2025; Flemish Parliament, committee C225, 2 Apr 2026
E-buses De Lijn ordered in 2025652De Lijn, 5 Jun 2026
De Lijn buses on order“almost eight hundred” (minister, Apr 2026)Flemish Parliament, 2 Apr 2026
Extra Flemish moneyEUR 400 million one-off in 2025; total rolling-stock budget 2025 EUR 483.5 millionMinister De Ridder, 29 Apr 2025; Policy note MOW 2024-2029, 15 Nov 2024
Pace after 2025~200 e-buses a year; 2025 orders arrive until 2028Flemish Parliament, 2 Apr 2026; De Lijn, e-bus page
2035 end state3,800 e-buses on ~140 depots (2,250 De Lijn + ~1,550 private)Flemish Parliament, 2 Apr 2026; newmobility.news, 16 Apr 2026
Cost of full electrification 2020-2035EUR 3.9 billion (existing depots) to EUR 5.2 billion (new depots); an e-bus costs about twice a diesel bus (~EUR 250,000)Flemish Parliament hearing, 20 Apr 2021 (older); De Lijn, cost page
De Lijn depots with chargers12 depots, 419 charge points at end-2025; works under way at “about 20” sitesDe Lijn, 5 Jun 2026; VRT NWS, 15 Apr 2026

Fleet totals differ by source: De Lijn uses 2,250, 2,149 and “over 2,000” for its own buses, and 3,600 or 3,800 for the whole system. This page uses 3,800 because it is the figure the minister uses in 2026.

The policy: zero-emission before 2035

The rule comes from the Flemish coalition agreement 2019-2024 (p. 203), quoted in a government note of 10 July 2020: “We laten in de nieuwe aankoopprocedures enkel zero-emissiebussen toe. … Ten laatste vóór 2035 rijden alle bussen in heel Vlaanderen emissievrij. Ook de (private) onderaannemers van De Lijn worden hierbij maximaal betrokken.” In plain words: new purchase procedures admit only zero-emission buses, city centres were to be served emission-free by 2025, and every bus in Flanders must be emission-free before 2035, private operators included (Flemish Government, VR 2020 1007 MED.0237/1BIS, 10 Jul 2020). The 2025 city-centre goal was not met; De Lijn’s director-general told parliament in 2021 it was not feasible (Flemish Parliament, doc 986, 2021-2022). Every De Lijn bus order since December 2021 has been battery-electric.

The 2024-2029 government kept the date and added money. The policy note of minister Annick De Ridder says De Lijn “houdt vast aan de doelstelling om tegen 2035 volledig emissievrij openbaar vervoer aan te bieden” and announces “een extra grote investeringsimpuls van 400 miljoen euro bij het begin van deze regeerperiode voor nieuwe elektrische bussen en trams”: a one-off EUR 400 million for new electric buses and trams at the start of the term, to be ordered in the first half of 2025 within existing framework contracts (Flemish Parliament, doc 124, 15 Nov 2024). The minister confirmed the EUR 400 million on 29 April 2025, with 225 standard and 150 articulated e-buses before the summer and a further order in the autumn (De Ridder, 29 Apr 2025). The money was one-off: the 2026 budget falls back, and De Lijn must save EUR 35.5 million in 2026 (Flemish Parliament, 2 Dec 2025; De Lijn, 5 Jun 2026).

The public service contract (openbaredienstencontract, ODC) 2023-2027, approved on 2 July 2022, fixes the interim steps: Euro 3 and Euro 4 buses out by early 2025, 80 % of Euro 5 out by end-2027, an investment budget raised by EUR 120 million a year to over EUR 260 million, EUR 573 million of greening investments in 2023-2027, and the private operators’ share of kilometres rising from 48 % to 53 % (De Lijn, 2 Jul 2022). A new contract running to 2035 is being prepared. Above all of this sits the EU Clean Vehicles Directive (EU) 2019/1161: for Belgium 45 % of buses bought under public contracts in 2021-2025 and 65 % in 2026-2030 must be “clean”, half of them zero-emission (Stibbe, 19 Jul 2019, older). De Lijn’s own climate plan adds -46.2 % greenhouse gases by 2030 and climate-neutral infrastructure by 2045 (Flemish Parliament, 2 Apr 2026).

De Lijn’s own electric fleet, by maker

Battery-electric buses that De Lijn owns or has on firm order add up to roughly 970, in line with the government’s aim of about 1,000 own e-buses by 2029 (VRT NWS, 15 Apr 2026). The links go to this site’s specification sheets.

BusLengthUnitsStatus (Oct 2026)Source
VDL Citea SLF-120 Electric (previous generation)12 m13In service since 2020-22; 6 of them in the Leuven pilot with Fluvius and ABBPitane Blue, 27 Nov 2020 (older)
Van Hool A12 LF E12 m36In service 2023-24 at Genk-Winterslag and Kortrijk; the last Van Hool city buses before the April 2024 bankruptcyDe Lijn, 2 Dec 2021 (older)
VDL Citea LF-122 (new generation)12 m24In service since 1 Jul 2024, Destelbergen (10) and Sint-Niklaas (14); 490 kWh, built in RoeselareSustainable Bus, 1 Jul 2024
CRRC midi bus via Yes-EU8.5 m137 in Bruges (summer 2023), 6 in Mechelen (Nov 2024, ~EUR 350,000 each)Sustainable Bus, 14 Oct 2024; newmobility.news, 11 Oct 2024
VDL Citea LF-181 trambus (HOV Hasselt-Maasmechelen)18 m17Ordered 24 Jan 2023; passenger service not confirmed by an official sourceMinister Peeters, 24 Jan 2023 (older); VRT NWS, 26 Feb 2026
Iveco Bus E-Way 18 m18 m241 (109 + 32 + 100)109 in service from Apr 2025, 32 from the 2025-26 year change, 100 from Q4 2026; 623 kWh; 86 withdrawn for two weeks in May-June 2026 (see risks)De Lijn, 28 Apr 2025; De Lijn, 19 Nov 2024; Iveco Group, 18 Jun 2025
BYD B12.b (first batch known as K9UD)12 m500 (92 + 140 + 268)92 in service from 23 Jun 2025 (Mortsel, Bruges, Hasselt, Genk); 140 from end-2026; 268 from Q2 2027; built in Komárom, HungaryDe Lijn, 4 Jan 2024; VRT NWS, 12 Jun 2025; De Lijn, 10 Dec 2025
VDL Citea LF-181 articulated18 m50Ordered 12 Jun 2025, built in Roeselare, first from end-2026/2027VRT NWS, 12 Jun 2025
Mercedes-Benz eCitaro12 m“over 80” first call-offFramework for up to 500, awarded Nov 2025; first buses from Q1 2027De Lijn, 10 Dec 2025; electrive, 11 Dec 2025
Irizar ie tram (HOV/BRT)18 m0 called offFramework for up to 100 signed May 2024 for Limburg and Kortrijk; no order foundelectrive, 7 May 2024 (older)
Plug-in e-hybrids (Van Hool, VDL)12/18 m324Interim step, not zero-emission; in servicePolicy note MOW, 15 Nov 2024

Why BYD: De Lijn said BYD could deliver in six months where competitors needed 18 to 24 (VRT NWS, 10 Dec 2025). The cybersecurity of Chinese buses was debated in the Flemish Parliament on 27 November 2025; De Lijn separates the vehicle network from telematics and requires UN regulation R156 in tenders (Flemish Parliament, 27 Nov 2025). What this means for an importer is on the makers page.

Framework contracts and orders, in order of date

De Lijn buys through framework contracts: a maker wins the right to supply up to a ceiling for several years, and De Lijn then “calls off” batches. Winning a framework does not guarantee a single bus (see Irizar).

DateContractVolume and valueSource
Jun 2021Framework standard e-buses, won by Van Hool and VDLUp to 350 buses, EUR 190-230 million incl. chargingPersinfo, 1 Jun 2021 (older)
2 Dec 2021First call-off: 36 Van Hool + 24 VDL; chargers split between SPIE-Ekoenergetyka and Heliox~EUR 28 million, 11 bidders, NextGenerationEU fundsDe Lijn, 2 Dec 2021 (older)
24 Jan 202317 VDL 18 m trambuses for Hasselt-MaasmechelenValue not publishedPeeters, 24 Jan 2023 (older)
Feb 2023Iveco Bus framework, E-Way 18 mUp to 500 buses over 2+2+2 years; 109 ordered in 2023DVO, 9 Feb 2023 (older)
24 Mar 2023New tenders: standard e-buses (up to 500, 6 years) and HOV e-buses (up to 100, 4 years)—De Lijn, 24 Mar 2023 (older)
27 Nov 2023Depot charging framework: SPIE-Ekoenergetyka and ABBUp to 1,600 charge points over 8 years; first tranche 320-490 points, EUR 15.3 million for 490De Lijn, 27 Nov 2023 (older)
4 Jan 2024BYD Europe framework, standard 12 m; first call-off 92Up to 500 buses; 92 for over EUR 43 millionDe Lijn, 4 Jan 2024 (older)
Early 2024 / 21 Feb 2025Second charger order to SPIE-EkoenergetykaEUR 24.2 million (the two parties date it differently)Ekoenergetyka, 18 Sep 2025
May 2024Irizar e-mobility framework, HOV e-busesUp to 100electrive, 7 May 2024 (older)
19 Nov 2024Iveco call-off, 32 articulated~EUR 24 millionDe Lijn, 19 Nov 2024 (older)
12 Jun 2025290 buses: BYD 140 (12 m), Iveco 100 (18 m), VDL 50 (18 m, Roeselare)EUR 185 millionVRT NWS, 12 Jun 2025
Nov-Dec 2025Daimler Buses framework eCitaro (up to 500) with first call-off “over 80”; BYD call-off 268, completing its frameworkDaimler framework max EUR 303 million; 2025 total 652 busesDe Lijn, 10 Dec 2025; De Lijn, 5 Jun 2026

No De Lijn bus order was found for September or October 2026.

Depots: the real bottleneck

De Lijn has about 50 own depots and the private operators about 90; all must be rebuilt for charging (De Lijn, strategy pages). At end-2025, 12 De Lijn depots had 419 charge points (De Lijn, 5 Jun 2026). The obstacles De Lijn lists are a full rebuild of each site, a medium-voltage cabin, fire-service and insurer demands (fire walls, retention of fire water), and permits that are contested: “Vergunningen krijgen is niet eenvoudig en wordt soms aangevochten” (VRT NWS, 15 Apr 2026). Since e-buses now manage 300-350 km a day, De Lijn charges overnight in the depot and has given up on fast charging at termini (Flemish Parliament, committee C248, 30 Apr 2026). A depot needs on average 10 MVA from the grid, about the connection of 1,000 households; Fluvius and De Lijn have worked under a framework agreement since 26 November 2020 and meet monthly (Fluvius, 26 Nov 2020, older; Flemish Parliament, 30 Apr 2026).

DepotStatus and figuresSource
Mortsel / Deurne Luchthaven (Antwerp)New climate-neutral depot since 1 Sep 2024, EUR 22 million; 84 charge points (Mar 2026), 155 during 2027; room for ~150 e-buses; 34 BYD buses; set to be the largest e-bus depotDe Lijn, 4 Jul 2023; De Lijn, 10 Mar 2026
Sint-NiklaasElectrified in phases since 2022; 62 charge points (Mar 2026); 14 VDL LF-122 and 34 Iveco 18 m; 34 Ekoenergetyka Axon Side 120/150 kWDe Lijn, 2 Mar 2026; De Lijn, 13 Aug 2025; Ekoenergetyka, 18 Sep 2025
Genk-Winterslag60 charge points; two medium-voltage cabins (2024); Van Hool A12, Iveco 18 m, trambuses; Ekoenergetyka Link Charger 500 kWVRT NWS, 27 May 2025; Ekoenergetyka, 18 Sep 2025
Hasselt-Crutzen85 charge points; 68 Axon Side 120/150 kW; 53 e-buses planned; first BYD in service 18 Dec 2025VRT NWS, 27 May 2025; De Lijn, 18 Dec 2025
Leuven-NoordPilot depot since Sept 2020 (VDL, ABB/Equans, Fluvius); first Iveco 18 m on 28 Apr 2025De Lijn, 28 Apr 2025
Destelbergen (Ghent)SPIE chargers 2022; VDL LF-122 since Jul 2024; Iveco 18 m 2025-26Sustainable Bus, 1 Jul 2024
Kortrijk, Bruges, Zomergem, Tielt-Winge, Broechem, MechelenElectrified; Bruges and Zomergem are public-private sites and the main 2024 investment (EUR 48.8 million for depot greening that year, mainly these two)De Lijn, e-bus page; Flemish Government, budget execution 2024
Ghent Wissenhage / Wondelgem (new tram and bus depot)Permit of 28 Jul 2024 annulled by the permits court on 23 Oct 2025; De Lijn is redoing part of the study; “crucial for greening in Ghent”Flemish Parliament, written question 211, 27 Oct 2025; Flemish Parliament, 30 Apr 2026
Rumst (maintenance centre), Asse/Mollem (new depot)Rumst permitted end-2021; Asse permit application autumn 2026, construction tentatively 2028-29De Lijn, 4 Jul 2023; Persinfo, 2026

Who supplies the chargers

The private operators and their subsidy

About half of the kilometres are driven by the 79 private operators (exploitanten or pachters): 69 million km in 2024 against 83 million by De Lijn itself, with the share moving towards them under the contracts that started on 1 July 2025 (Flemish Parliament, doc 513, 9 Oct 2025). They electrify faster than De Lijn: 277 e-buses (16 %) at end-2024, 588 (36 %) from 1 July 2025, over 700 (45 %) in April 2026 (Flemish Parliament, 2 Dec 2025; Flemish Parliament, 2 Apr 2026). Their new contracts contain a greening pace towards 100 % zero-emission in 2035, and they must pay for their own depots: “grid access is not always obvious” (same source).

The subsidy. On 2 March 2022 minister Lydia Peeters, De Lijn and the operators’ federation FBAA agreed, under the Flemish Climate Plan, that an operator receives up to EUR 21,700 a year per zero-emission bus that replaces a diesel bus within an existing contract, for three years; about 300 extra e-buses were expected (Sustainable Bus, Mar 2022; PV Magazine NL, 2 Mar 2022, older). Since 1 July 2025 the incentive sits inside the new contracts rather than as a separate scheme (Flemish Parliament, 2 Apr 2026). No decree text was found. The rules and money page has the wider picture.

OperatorElectric buses and chargersSource
Hansea (Antwerp; owned by DWS Infrastructure)Largest contractor: over 1,340 vehicles, over 375 zero-emission, 21 sites (Sept 2025); 181 MAN Lion’s City E ordered 6 Aug 2024 on top of 90 in service; also Daimler, Irizar and Yutong per press; 160 Ekoenergetyka chargers at 15 sites; whole fleet electric by 2035MAN Belgium, 6 Aug 2024; Ekoenergetyka, 18 Sep 2025
Keolis Belgium (SNCF group)Second-largest; e-buses from MAN/Neoplan, Iveco and Karsan per press; 78 fast chargers and 17 mobile charging posts; 26 × 150 kW at Neder-Over-HeembeekFBAA Car & Bus, Aug 2026
Multiobus (Tienen)First private operator with e-buses for De Lijn (2018); 36 Ebusco buses (2.1, 2.2 and 3.0) after a 20-bus order in Oct 2023; overnight charging on own green powerEbusco, 9 Oct 2023 (older)

Low-emission zones and the fines

Ghent and Antwerp have low-emission zones, and late e-bus deliveries put De Lijn on the wrong side of them. In the first half of 2025 De Lijn paid almost EUR 125,000 in about 800 fines in Ghent, three times the 2024 figure: “We betalen liever een boete dan dat we ritten moeten schrappen”, we would rather pay a fine than cancel trips (VRT NWS, 29 Oct 2025). At end-2025, 56 Euro 3 diesel buses still ran from depots serving the two zones; about 90 % of the fines come from Ghent; the Flemish Government decided in November 2025 to withdraw the tightening of the zones planned for 2026 (Flemish Parliament, 2 Apr 2026). Delay penalties are charged to the suppliers but do not cover the fines.

The builders left in Flanders

Van Hool is gone as a bus builder. The Koningshooikt (Lier) company filed for bankruptcy on 5 April 2024; about 2,400 people lost their jobs; VDL Groep and Schmitz Cargobull bought the assets and VDL kept about 250 jobs in Koningshooikt for parts, after-sales and development, with bus assembly moving to VDL’s plants and the coach plant in North Macedonia (VRT NWS, 11 Jun 2024; VRT NWS, 7 Apr 2026). The 30 ha site was auctioned in June 2026 for EUR 21.5 million (the Flemish Government bid EUR 20 million and lost) and resold in July 2026 to the Dutch contractor Mourik (VRT NWS, 19 Jun 2026; VRT NWS, 6 Jul 2026). The 36 A12 LF E of 2023-24 were its last city buses for De Lijn.

VDL Bus Roeselare (the former Jonckheere) is the only city-bus plant left in Belgium. The new factory at Krommebeekpark opened on 10 April 2024: a 27,000 m² hall on a 77,000 m² site, capacity about 800 buses a year, building the new-generation Citea (VDL Groep, 10 Apr 2024). De Lijn’s 24 Citea LF-122, 17 trambuses and 50 Citea LF-181 are built there. At the opening VDL’s bus chief asked for “een eerlijke wedstrijd, een wedstrijd met dezelfde spelregels”, a fair contest on the same rules, aimed at Chinese builders; the BYD orders of 2024 and 2025 drew the same criticism in the Flemish Parliament (VRT NWS, 10 Dec 2025). Yes-EU is the Belgian dealer of CRRC and Yutong and supplied De Lijn’s 13 midi buses (Sustainable Bus, 14 Oct 2024).

Risks and incidents, 2025-2026

What this page could not confirm

Research closed 28 October 2026. Corrections through the contact page.